ORDINANCE NO. 220658
title
Authorizing a $4,448,000.00 construction contract with Infrastructure Solutions LLC, for the Inflow and Infiltration (I/I) Reduction: Middle Blue River Area 13 project; authorizing a maximum expenditure of $4,850,000.00; and, authorizing a $496,000.00 Design Professional Services Amendment No. 1 to Contract No. 1510 with CH2M Hill Engineers, Inc., for a total contract amount of $1,046,000.00.
body
BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:
Section 1. That the Director of the Water Services Department is authorized to execute Contract No. 1529 in the amount of $4,448,000.00 with Infrastructure Solutions LLC, for the I/I Reduction: Middle Blue River Area 13 project, Project No. 81000720. A copy of the contract is on file in the office of Water Services.
Section 2. That the Director of Water Services is authorized a maximum expenditure of $4,850,000.00, from previously appropriated funds in the following Account No.
AL-8188-807769-611060-81000720 Overflow Control Program $4,448,000.00
23-8110-807769-B-81000720 Overflow Control Program 402,000.00
TOTAL $4,850,000.00
Section 3. That the Director of the Water Services Department is authorized to execute Design Professional Services Amendment No. 1 to Contract No. 1510 in the amount of $496,000.00, for a total contract amount of $1,046,000.00, with CH2M Hill Engineers, Inc., for the I/I Reduction: Middle Blue River Area 13, Project No. 81000720. A copy of the contract is on file in the office of Water Services.
Section 4. That the Director of the Water Services Department is authorized a maximum expenditure of $496,000.00, from Account No. AL-8188-807769-611040-81000720, Overflow Control Program, to satisfy the cost of this amendment.