ORDINANCE NO. 241017
title
Sponsor: Director of Water Services Department
Authorizing a $6,885,000.00 design-build contract with Kissick Construction Company, Inc., for Renewal No. 3 for the City-Wide Sewer Infrastructure Rehabilitation within Waterways Project.
body
WHEREAS, City Council passed Ordinance No. 170032 on January 26, 2017, authorizing $6,885,000.00 Design-Build Contract Number 1275 with Kissick Construction Company, Inc., for design and build services of the City-Wide Sewer Infrastructure Rehabilitation within Waterways Project; and
WHEREAS, City Council passed Ordinance No. 180345 on June 7, 2018, authorizing $6,885,000.00 Design-Build Contract Number 1493-1 with Kissick Construction Company, Inc., for design and build services of the City-Wide Sewer Infrastructure Rehabilitation within Waterways Project, Renewal No. 1; and
WHEREAS, City Council passed Ordinance No. 210978 on November 10, 2021, authorizing $6,885,000.00 Design-Build Contract Number 1493-2 with Kissick Construction Company, Inc., for design and build services of the City-Wide Sewer Infrastructure Rehabilitation within Waterways Project, Renewal No. 2; and
WHEREAS, this proposed $6,885,000.00 ordinance under Contract No. 1493-3 is for the third and final renewal option for the City-Wide Sewer Infrastructure Rehabilitation within Waterways Project; NOW, THEREFORE,
BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:
Section 1. That the Director of the Water Services Department is authorized to execute Contract Renewal No. 3, for Contract No. 1493-3 in the amount of $6,885,000.00 with Kissick Construction Company, Inc., for the City-Wide Sewer Infrastructure Rehabilitation within Waterways Project, Project No. 81000756. A copy of the contract is on file in the office of Water Services.
Section 2. That the Director of Water Services Department is authorized to expend up to $6,885,000.00 from the following accounts to satisfy the cos...