ORDINANCE NO. 230478
title
Sponsor: Director of the Water Services Department
Authorizing a $3,864,415.00 construction contract with Hartline Construction, LLC, for the Water Services Administration Building and I/T Improvements and ADA Compliance project; authorizing a maximum expenditure of $4,239,415.00; authorizing a $292,195.00 design professional services Amendment No. 4 to Contract No. 1519,for the Various Building and I/T Improvements and ADA Compliance Implementation Water Services Department Building (SLBE-WSDEPS) project with Wellner Architects, Inc., for a total contract amount of $750,195.00; and recognizing this ordinance as having an accelerated effective date.
body
WHEREAS, the City approved a $187,938.00 design professional services Contract No. 1519 with Wellner Architects, Inc. on October 30, 2019, for the Various Building and I/T Improvements and ADA Compliance Implementation Water Services Department Building (SLBE-WSDEPS) project; and
WHEREAS, the City approved a $27,663.00 Amendment No. 1 on September 21, 2020, and a $177,399.00 Amendment No. 2 on February 22, 2021, for Contract No. 1519 with Wellner Architects, Inc. for planning, design changes, and I/T upgrade work on the design professional services project; and
WHEREAS, City Council approved Ordinance No. 210438 on May 27, 2021, authorizing a $65,000.00 Amendment No. 3 to Contract No. 1519 with Wellner Architects, Inc. for I/T updates and gender neutral restroom design work on the design professional services project; and
WHEREAS, this proposed ordinance is requesting City Council approval for a $292,195.00 Amendment No. 4 to Contract No. 1519 with Wellner Architects, Inc., for construction phase services on the project for a total contract amount of $750,195.00; NOW, THEREFORE,
BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:
Section 1. That the Director of the Water Services Department is authorized to execute construction...