File #: 241065    Version: Name:
Type: Ordinance Status: Agenda Ready
File created: 11/22/2024 In control: Neighborhood Planning and Development Committee
On agenda: 1/7/2025 Final action:
Title: Sponsor: Director of City Planning and Development Department COMMITTEE SUBSTITUTE Approving a development plan on about 7.6 acres in District KCIA generally located at 10220, 10200, and 10150 N. Everton Avenue to allow for one industrial logistic/warehouse building. (CD-CPC-2024-00107)
Attachments: 1. Docket Memo 0.1.5, 2. 15_CD-CPC-2024-00107_StaffReport_Project Maartin, 3. CPC Dispo Letter, 4. CPC PPT_Project Maartin, 5. CPC Recommend Approval Plans
committeesub
[COMMITTEE SUBSTITUTE FOR]ORDINANCE NO. 241065

title
Sponsor: Director of City Planning and Development Department
COMMITTEE SUBSTITUTE

Approving a development plan on about 7.6 acres in District KCIA generally located at 10220, 10200, and 10150 N. Everton Avenue to allow for one industrial logistic/warehouse building. (CD-CPC-2024-00107)

body
BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

Section A. That a development plan in District KCIA generally located at 10220, 10200, and 10150 N. Everton Avenue, and more specifically described as follows:

All of Lots 1, 2 & 3, KCI Industrial Park, a subdivision of land in the City of Kansas City, Platte County, Missouri.

is hereby approved, subject to the following conditions:

1. The proposed development is located in an area where the Kansas City International Airport (MCI) height zoning restrictions apply. No structure in this area should be constructed which exceeds these restrictions. Per FAR Part 77, Objects Affecting Navigable Airspace, the proponent/developer shall file an on-line Form 7460-1, Notice of Proposed Construction or Alteration, for new structures and receive a Determination of No Hazard to Air Navigation from the FAA. Temporary cranes used for construction activities extending higher than the proposed top elevation of the building will need to be evaluated for compliance with FAR Part 77 standards as well. 7460s must be submitted a minimum of 45 days prior to the start date of the proposed construction or alteration. The FAA's Obstruction Evaluation/Airport Airspace Analysis (OE/AAA) website can be accessed at https://oeaaa.faa.gov/ oeaaa/external/portal.jsp. It is further recommended the proponent/developer provide the FAA with a 1A survey accuracy statement assuming the highest horizontal and vertical tolerance was used for this design. This information certifies the ground elevations the developer has portrayed within the plans are to higher level of accuracy....

Click here for full text