File #: 260590    Version: 1 Name:
Type: Ordinance Status: Referred
File created: 6/25/2026 In control: Transportation, Infrastructure and Operations Committee
On agenda: 7/7/2026 Final action:
Title: Sponsor: Director of Water Services Department Authorizing the Director of Water Services to execute a $9,417,389.20 Amendment No. 1 for Phase 2 services to the progressive design-build contract with Burns & McDonnell Engineering Company, Inc., for the Northland Transmission, Pumping and Storage project for a total contract amount of $10,517,389.20; and recognizing this ordinance as having an accelerated effective date.
Sponsors: Director of Water Services
Attachments: 1. 9977 Original Approved Bid Recommendation, 2. 9977 Original Bid Opening Summary, 3. 9977 Approved MWBE Goals, 4. 9977 Original CUP Approval & CUP Summary, 5. 9977 Original CUP Documents Submitted, 6. 9977 Amendment 1 Docket Memo
ORDINANCE NO. 260590

title
Sponsor: Director of Water Services Department

Authorizing the Director of Water Services to execute a $9,417,389.20 Amendment No. 1 for Phase 2 services to the progressive design-build contract with Burns & McDonnell Engineering Company, Inc., for the Northland Transmission, Pumping and Storage project for a total contract amount of $10,517,389.20; and recognizing this ordinance as having an accelerated effective date.

body
WHEREAS, City Council passed Ordinance No. 260268 on April 2, 2026, authorizing a $1,100,000.00 progressive design-build contract with Burns & McDonnell Engineering Company, Inc., for the Northland Transmission, Pumping and Storage project; and

WHEREAS, this proposed $9,417,389.20 Amendment No. 1 is for engineering design and field investigation Phase 2 services for additional design services for the 2027 interim solution and early procurement of long lead items for the interim solution at existing Water Treatment Plant Secondary Pump Station, including the replacement of Pump #6 with a new 20 million gallon per day pump, and the provision of associated electrical equipment; NOW, THEREFORE,

BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

Section 1. That the Director of Water Services Department is authorized to execute Amendment No. 1 to Contract No. 9977 in the amount of $9,417,389.20, for a total contract amount of $10,517,389.20, with Burns & McDonnell Engineering Company, Inc., for the Northland Transmission, Pumping and Storage project, Project No. 80002662. A copy of this amendment is on file in the office of Water Services.

Section 2. That the Director of Water Services is authorized to expend up to the sum of $9,417,389.20 from the following accounts to satisfy the cost of this amendment:

AL-8079-807772-611040-80002662 Water Pump Stations $ 104,539.24
AL-8082-807772-611040-80002662 Water Pump Stations 7,735,460.76
27-8010-807772-634240-80002662 Wate...