ORDINANCE NO. 250144
title
Sponsor: Director of Water Services Department
Authorizing a $3,054,685.69 design professional services contract Amendment No. 2 to Contract No. 1587 with Burns & McDonnell Engineering Company, Inc., for the Todd Creek Facility Plan Update project for a total contract amount of $9,493,916.69; and recognizing this ordinance as having an accelerated effective date.
body
WHEREAS, City Council passed Ordinance No. 200317 on May 14, 2020, authorizing an $801,029.00 design professional services contract with Burns & McDonnell Engineering Company, Inc., for the Todd Creek Facility Plan Update project; and
WHEREAS, City Council passed Ordinance No. 210723 on September 23, 2021, authorizing a $5,638,202.00 Amendment No. 1 to the design professional services contract with Burns & McDonnell Engineering Company, Inc., for the Todd Creek Facility Plan Update project for development of the selected alternative identified in the Facility Plan through 100% design, and development of bid documents; and
WHEREAS, this ordinance is for a $3,054,685.69 Amendment No. 2 for redesign of the treatment plant to the new proposed southern site fully within City limits in accordance with the City Council's desire expressed in Ordinance No. 230975; NOW, THEREFORE,
BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:
Section 1. That the Director of Water Services Department is authorized to execute Amendment No. 2 to Contract No. 1587 in the amount of $3,054,685.69, for a total contract amount of $9,493,916.69 with Burns & McDonnell Engineering Company, Inc., for the Todd Creek Facility Plan Update project, Project No. 81000927. A copy of this amendment is on file in the office of Water Services.
Section 2. That the Director of Water Services is authorized to expend up to the sum of $3,054,685.69 from the following accounts in order to satisfy the cost of this amendment:
AL-8187-807778-611040-8100...