File #: 240930    Version: 1 Name:
Type: Ordinance Status: Referred
File created: 10/9/2024 In control: Transportation, Infrastructure and Operations Committee
On agenda: 10/29/2024 Final action:
Title: Sponsor: Director of Water Services Department Authorizing a $7,500,000.00 construction contract with Superior Bowen Asphalt Co., LLC, for the WD Asphalt and Concrete, City Wide, Renewal No. 1 project; and authorizing modifications to the contractual commitment between funds as long as the total contract amount does not change.
Sponsors: Director of Water Services
Attachments: 1. 9835 Approved Goals, 2. 9835 Bid Opening Summary, 3. 9835 CUP Document Submttal, 4. 9835 Original CUP Approval, 5. 9835 Orignal CUP Summary, 6. 9835 Signed Bid Recommendation, 7. 9835-1 Docket Memo, 8. 9835-1 Construction Contract
ORDINANCE NO. 240930

title
Sponsor: Director of Water Services Department

Authorizing a $7,500,000.00 construction contract with Superior Bowen Asphalt Co., LLC, for the WD Asphalt and Concrete, City Wide, Renewal No. 1 project; and authorizing modifications to the contractual commitment between funds as long as the total contract amount does not change.

body
WHEREAS, City Council passed Ordinance No. 231024 on December 14, 2023, authorizing a $7,500,000.00 construction contract with Superior Bowen Asphalt Co., LLC, for the WD Asphalt and Concrete, City Wide project and one successive renewal with further City Council approval; and

WHEREAS, this proposed $7,500,000.00 ordinance under Contract No. 9835-1 is for the first and final renewal option for the WD Asphalt and Concrete, City Wide, Renewal No. 1 project; NOW, THEREFORE,

BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

Section 1. That the Director of Water Services Department is authorized to execute Contract No. 9835-1 in the amount of $7,500,000.00 with Superior Bowen Asphalt Co., LLC, for the WD Asphalt and Concrete, City Wide, Renewal No. 1 project, Project No. 60XX0028. A copy of this contract is on file in the office of Water Services.

Section 2. That the Director of Water Services Department is authorized to expend up to $7,500,000.00 from the following accounts to satisfy the cost of this contract:

25-8010-802010-B Distribution - Pipeline $5,000,000.00
25-8110-802040-B Maintenance - Sewer Repair 1,400,000.00
25-8200-802301-B Catch Basin Cleaning & Repair 100,000.00
25-8010-807705-611060-60XX90028 WSD Asphalt & Concrete Restor 1,000,000.00
TOTAL $7,500,000.00

Section 3. That the Department is authorized to modify the contractual commitment between the funds listed in Section 2 as long as the total contract amount does not change.

end