File #: 240349    Version: 1 Name:
Type: Ordinance Status: Passed
File created: 3/28/2024 In control: Council
On agenda: 4/11/2024 Final action: 4/11/2024
Title: Sponsor: Councilmembers Crispin Rea and Eric Bunch Authorizing a $2,741,000.00 progressive design-build services contract with Burns & McDonnell Engineering Company, Inc., for Phase 1 services for the Dr. Jeremiah Cameron Park and Westport Stormwater Improvements project; and providing for successive Phase 2 services subject to City Council approval.
Sponsors: Crispin Rea, Eric Bunch
Attachments: 1. 240349 Docket Memo - Revised, 2. Docket Memo 240349, 3. Ordinance 240349-CUP Summary-470.pdf, 4. 470 Progressive Design Build RFQ, 5. Citywide Selection Committee, 6. Shortlist Recommendation Memo, 7. 240349 4-10-2024 TIO Presentation, 8. Authenticated Ordinance 240349
ORDINANCE NO. 240349

title
Sponsor: Councilmembers Crispin Rea and Eric Bunch

Authorizing a $2,741,000.00 progressive design-build services contract with Burns & McDonnell Engineering Company, Inc., for Phase 1 services for the Dr. Jeremiah Cameron Park and Westport Stormwater Improvements project; and providing for successive Phase 2 services subject to City Council approval.

body
WHEREAS, this proposed ordinance is for authorization of Phase 1 design-build services based on Water Services Department project criteria and the level of completion required for Contractor and the Director of the Water Services Department to establish the Contract Price for subsequent Phase 2 design-build services, subject to City Council approval; and

WHEREAS, this project will be constructed in three construction packages under Phase 2 design-build services. The limits of the work in each construction package and the Contract Times will be determined based on the availability of project funding. The first construction package for this project will be for stormwater improvements work at Dr. Jeremiah Cameron Park and subsequent construction packages 2 and 3 will progress stormwater improvements along Mill Street to Southwest Trafficway; NOW, THEREFORE,

BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

Section 1. That the Director of the Water Services Department is authorized to execute Contract No. 470 in the amount of $2,741,000.00 with Burns & McDonnell Engineering Company, Inc., for Phase 1 design-build services for the Dr. Jeremiah Cameron Park and Westport Stormwater Improvements project, Project No. 82000379. A copy of the contract is on file in the office of Water Services.

Section 2. That the Director of the Water Services Department is authorized a maximum expenditure of $2,741,000.00 from Account No. Al-3625-808054-B-82000379, Jeremiah Park/Westport, to satisfy the cost of this contract.

Section 3. That the Director of the Wat...