COMMITTEE SUBSTITUTE FOR ORDINANCE NO. 220874
title
Sponsor: Director of Water Services Department
Authorizing a $9,100,000.00 Construction Contract with Goodwin Bros. Construction Co., for the Birmingham Pump Station Screen Replacement; authorizing a maximum expenditure of $10,222,300.00; and authorizing a $603,143.68 Design Professional Services Amendment No. 1 to Contract No. 1588, for the Birmingham Pump Station Screen Replacement project with Lion CSG, LLC, for a total contract amount of $931,766.68; and recognizing this ordinance as having an accelerated effective date.
body
BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:
Section 1. That the Director of the Water Services Department is authorized to execute Contract No. 1662 in the amount of $9,100,000.00 with Goodwin Bros. Construction Co., for the Birmingham Pump Station Screen Replacement project, Project No. 81000928. A copy of the contract is on file in the office of Water Services.
Section 2. That the Director of the Water Services Department is authorized a maximum expenditure of $10,222,300.00, from Account No. 23-8110-807777-B-81000928, Sewer Pump Stations, to satisfy the cost of this contract.
Section 3. That the Director of the Water Services Department is authorized to execute Design Professional Services Amendment No. 1 to Contract No. 1588 in the amount of $603,143.68, for a total contract amount of $931,766.68, with Lion CSG, LLC, for the Birmingham Pump Station Screen Replacement project, Project No. 81000928. A copy of the contract is on file in the office of Water Services.
Section 4. That the Director of the Water Services Department is authorized a maximum expenditure of $603,143.68, from Account No. AL-8189-807777-B-81000928, in the amount of $300,000.00, and 23-8110-807777-B-81000928, in the amount of $303,143.68, Sewer Pump Stations, to satisfy the cost of this amendment.
Section 5. That this ordinance, relating to the design, repair, maintenance or construc...