ORDINANCE NO. 260607
title
Sponsor: Director of the Public Works Department
Authorizing the Director of Public Works to execute a $1,497,596.45 construction contract with Sarai Construction, Inc. for sidewalk repairs; authorizing the Director of Public Works to enter contract changes by up to twenty percent (20%); and recognizing this ordinance as having an accelerated effective date.
body
BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:
Section 1. That the Director of Public Works is hereby authorized to execute a construction contract with Sarai Construction, Inc. for sidewalk repairs in the amount of $1,497,596.45 from funds previously appropriated to the following accounts:
AL-3527-898077-611060-89061151 FY26-27 CWA Citywide #1 $1,497,596.45
A copy of the contract is on file in the office of the Director of Public Works.
Section 2. That the Director of Public Works is hereby authorized to amend this contract and to increase the amount of the contract by up to twenty percent (20%) without further Council approval.
Section 3. That this ordinance, relating to the design, repair, maintenance or construction of a public improvement, is recognized as having an accelerated effective date provided by Section 503(a)(3)(D) of the City Charter and shall take effect in accordance with Section 503, City Charter.
end
______________________________________________________
I hereby certify that there is a balance, otherwise unencumbered, to the credit of the appropriation to which the foregoing expenditure is to be charged, and a cash balance, otherwise unencumbered, in the treasury, to the credit of the fund from which payment is to be made, each sufficient to meet the obligation hereby incurred.
___________________________________
Brenton Siverly
Director of Finance
Approved as to form:
___________________________________
Andrew Bonkowski
Assistant City Attorney