Title: Sponsor: Director of Water Services Department Authorizing the Director of Water Services to executed an $8,461,700.00 construction contract with MegaKC Corporation, for the Green Infrastructure Project 1-1: Mill Creek Park Green Infrastructure Phase 2-Retention Ponds project; authorizing a maximum expenditure of $9,300,000.00; and recognizing this ordinance as having an accelerated effective date.
Attachments: 1. 1804 Docket Memo, 2. 1804 Approved Bid Recommendation & Bid Opening Summary, 3. 1804 Approved MWBE Goals, 4. 1804 CUP Documents Submitted, 5. 1804 Construction Contract, 6. 1804 CUP Approval & CUP Summary, 7. 1804 Revised Docket Memo

ORDINANCE NO. 260492

 

title

Sponsor:  Director of Water Services Department

 

Authorizing the Director of Water Services to executed an $8,461,700.00 construction contract with MegaKC Corporation, for the Green Infrastructure Project 1-1: Mill Creek Park Green Infrastructure Phase 2-Retention Ponds project; authorizing a maximum expenditure of $9,300,000.00; and recognizing this ordinance as having an accelerated effective date.

 

body

WHEREAS, this proposed ordinance is for authorization of a construction project for the Green Infrastructure Project 1-1: Mill Creek Park Green Infrastructure Phase 2-Retention Ponds; NOW, THEREFORE,

 

BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

 

Section 1. That the Director of the Water Services Department is authorized to execute Contract No. 1804 in the amount of $8,461,700.00 with MegaKC Corporation for the Green Infrastructure Project 1-1: Mill Creek Park Green Infrastructure Phase 2-Retention Ponds project, Project No. 81000955.  A copy of the contract is on file in the office of Water Services.

 

Section 2. That the Director of Water Services Department is authorized to expend up to maximum of $9,300,000.00 from Account No. 27-8110-807769-611060-81000955, Overflow Control Program, to satisfy the cost of this contract. 

 

Section 4.  That this ordinance, relating to the design, repair, maintenance or construction of a public improvement, is recognized as an ordinance with an accelerated effective date as provided by Section 503(a)(3)(D) of the City Charter and shall take effect in accordance with Section 503, City Charter.

 

end

______________________________________________________

 

I hereby certify that there is a balance, otherwise unencumbered, to the credit of the appropriation to which the foregoing expenditure is to be charged, and a cash balance, otherwise unencumbered, in the treasury, to the credit of the fund from which payment is to be made, each sufficient to meet the obligation hereby incurred.

 

 

______________________________

Brenton Siverly

Director of Finance

 

Approved as to form:

 

 

______________________________

Mark P. Jones

Senior Associate City Attorney