ORDINANCE NO. 240608
title
Sponsor: Director of Water Services Department
Authorizing a $12,000,000.00 design professional services contract with Burns & McDonnell Engineering Company, Inc., for FY25 Smart Sewer Program Management Services; and recognizing this ordinance as having an accelerated effective date.
body
WHEREAS, under Ordinance No. 210347, the Water Services Department exercised the option to renew its design professional services contract with Burns & McDonnell Engineering Company, Inc., for the continuation of Overflow Control Program Management Services for renewals 4 - 7 of 9 one-year renewal options in accordance with RFQ/P solicitation for design professional services under Contract No. 1355, Overflow Control Program Management (Ordinance No. 170375). This RFQ/P solicitation was for one year with nine (9) one-year options to renew at the sole discretion of the City. The City previously exercised renewal options 1 - 6 of 9 one-year renewals under Contract Nos. 1538, 1597, 1597-3, 1635, 1635-1, and 1635-2; and
WHEREAS, this proposed Renewal No. 3 will have a 12-month base period, in the amount of $12,000,000.00, and is the third renewal option of three successive renewals subject to City Council approval (Ordinance No. 210347); NOW, THEREFORE,
BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:
Section 1. That the Director of the Water Services Department is authorized to execute Contract No. 1635-3, in the amount of $12,000,000.00, with Burns & McDonnell Engineering Company, Inc., for FY25 Smart Sewer Program Management Services, Project No. 60810092. A copy of the contract is on file in the office of Water Services.
Section 2. That the Director of the Water Services Department is authorized to expend up to $12,000,000.00 from the following accounts:
25-8110-807769-610300-60810092 |
Smart Sewer-Program Management |
$9,560,141.00 |
AL-8193-807769-611040-81000998 |
Storm Collection & GI- 37th & Norton |
$348,551.29 |
AL-8193-807769-611040-81000756 |
Sewer Rehab within Waterways |
$348,551.29 |
AL-8193-807769-611040-81000916 |
GI 2-1: 63rd and DMB Park |
$348,551.29 |
AL-8193-807769-611040-81000719 |
I/I Reduc Northern Basn Proj 1 |
$348,551.29 |
AL-8193-807769-611040-81000955 |
GI 1-1: Mill Creek Park |
$348,551.29 |
AL-8193-807769-611040-81000975 |
GI - Paseo Gateway |
$348,551.26 |
TOTAL |
|
$12,000,000.00 |
Section 3. That the Director of the Water Services Department is authorized to negotiate one successive renewal for this work subject to City Council approval.
Section 4. That this ordinance is recognized as an ordinance with an accelerated effective date as provided by Section 503(a)(3)(D) of the City Charter and shall take effect in accordance with Section 503, City Charter.
end
______________________________________________________
I hereby certify that there is a balance, otherwise unencumbered, to the credit of the appropriation to which the foregoing expenditure is to be charged, and a cash balance, otherwise unencumbered, in the treasury, to the credit of the fund from which payment is to be made, each sufficient to meet the obligation hereby incurred.
______________________________
Tammy L. Queen
Director of Finance
Approved as to form:
______________________________
Mark P. Jones
Senior Associate City Attorney