File #: 220375    Version: 1 Name:
Type: Ordinance Status: Agenda Ready
File created: 4/1/2022 In control: Council
On agenda: 4/28/2022 Final action:
Title: Authorizing the Director of Public Works to enter into a construction contract with J.M. Fahey Construction Co. in the amount of $8,988,266.76 for Project No. 22-3 - Resurface Designated Streets 43rd Street to the South City Limits; authorizing contract changes up to and including thirty percent (30%) of the original contract price; and recognizing this ordinance as having an accelerated effective date.
Attachments: 1. 220375 Fact Sheet, 2. 220375 Fiscal Note, 3. Ordinance 220375-22-3, 4. Authenticated Ordinance 220375, 5. Project Manual on File
Related files: 220373
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
ORDINANCE NO. 220375

title
Authorizing the Director of Public Works to enter into a construction contract with J.M. Fahey Construction Co. in the amount of $8,988,266.76 for Project No. 22-3 - Resurface Designated Streets 43rd Street to the South City Limits; authorizing contract changes up to and including thirty percent (30%) of the original contract price; and recognizing this ordinance as having an accelerated effective date.

body
BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

Section 1. That the Director of Public Works is hereby authorized to execute a contract with J.M. Fahey Construction Co. in the amount of $8,988,266.76 for Contract Number CS220040 street resurfacing 43rd Street to the South City Limits from funds previously appropriated to the following accounts:

AL-3523-897701-B-89008533 Street Preservation $6,666,667.00
23-3090-897701-B-89008533 Street Preservation 2,321,599.76
TOTAL: $8,988,266.76

Section 2. That the Fairness in Construction Board, to assure fair representation by socially and economically disadvantaged groups, approved for this project, a nine percent (9%) representation by Minority Owned Businesses and a seven percent (7%) representation by Women Owned Businesses.

Section 3. That the Director of Public Works is authorized to enter into contract changes up to and including thirty percent (30%) of the original contract price for related work. A copy of the contract is on file in the office of the Director of Public Works.

Section 4. That this ordinance, relating to the design, repair, maintenance or construction of a public improvement, is recognized as an ordinance with an accelerated effective date as provided by Section 503(a)(3)(D) of the City Charter and shall take effect in accordance with that section.
end
______________________________________________________

I hereby certify that there is a balance, otherwise unencumbered, to the credit of the a...

Click here for full text